The project of PLTU Lampung 2 X 100MW, a coal fired power plant, was initiated on March 2008 (groundbreaking). The project is located at dusun Sebalang, Tarahan village, Southern Lampung county.
PLN, owner of this USD +/- 200 million project, awarded ADHI to handle it. According to the plan, unit 1 will be finished within 30 months and 3 months later, unit 2 will also be finished. On this project, ADHI join with a Chinese company, Jiangxi Electrical Overseas Engineering Co., Ltd.